As you are all aware the Campus is very busy at the moment. Below is the schedule of painting works being carried out in the halls and village  to make ready for summer lets and new term.

Cromwell has guests next week from the 17th July then painting commences the week after on the 24th July.

Hudson is being painted and cleaned this week and next week then guests move in on 24/7. We then have a week to clean and make rooms ready for the next guests on the 7/8

Clark will be cleaned next week and made ready for guests arriving on the 24/7. We then have a week to clean and make rooms ready for the next guests on the 7/8. Painting then commences on the 15/8

Coleridge is being painted and cleaned this week and next week and the SKE students return on the 22/7 and will be staying in residence until 26/8

KSW has guests next week then painting will take place the following week 24/7. Once painting has finished it will require cleaning and make ready for potential lets.

Tufnell is being let on 24/7 and 31/7. The painting will take place the following week from 7/8.

Dix is being let 17/7 to 25/7. Then it will need to be cleaned and remade for new guests on the 31/7. Painting will take place the following week from 7/8. There will be another potential let on 28/8.

Please be aware that there should be no access in the halls while the painting is undertaken for Health and Safety reasons.

Works in the village are on going with external painting continuing and kitchen and shower refurbishment on going. Also cleaning and making rooms ready are on going where possible to make ready for the guests we have arriving on 3/8. The guests will be residing in the majority of the village for 2 weeks. Painting will then take place from 20/8 until start of term.

Please be aware that there should be no access to the village whilst work continues.

There will also be various other painting and carpet fitting taking place around the Campus but I will inform you as and when it is confirmed.