Good morning
No works were carried out on site last week due to exams being held on campus
House 29
A new steel beam will be installed this week - once this is completed work will begin to install the new kitchen units to provide a new kitchen/diner facility.  Decoration and flooring works will follow. 
Work is due to continue on houses 17 - 24 including decoration and upgrading of fascias, guttering and soffits.  There will be ongoing scaffold removals and installation as work moves around the village site.  Efforts will be made to keep any noise to a minimum during scaffold changes.
Alison